Time Tracker

Build started June 29, 2022

🔧 = in progress
= completed

Empennage and Tail Cone

  6 - Vertical Stabilizer                  34.3 hours               June 29 - September 5 2022
  7 - Rudder                                    41.7 hours               July 8 - September 4 2022
  8 - Horizontal Stabilizer             87.7 hours               July 16 - October 24 2022
  9 - Elevators                               116.3 hours              September 14 2022 - November 30 2024
10 - Tail Cone                              164.8 hours               January 8 2023 - June 3 2024
11 - Empennage Attach                 7.8 hours  🔧             Started August 15 2023

Total                                             452.6 hours

Wings

13 - Main Spar                               39.9 hours               July 6 2023 - January 13 2024
14 - Wing Ribs                                48.8 hours              August 27 2023 - March 27 2024
15 - Rear Spar                                32.7 hours              August 28 2023 - April 5 2024
16 - Top Wing Skins                      60.6 hours              January 19 2024 - June 27 2024
17 - Outboard Leading Edge        56.0 hours              September 18 2023 - June 30 2024   
18 - Fuel Tank                                38.7 hours ðŸ”§             Started October 1 2023 
19 - Stall Warning System              SKIPPED                                              
20 - Bottom Wing Skin                   8.9 hours ðŸ”§             Started May 25 2024                              
21 - Aileron                                    49.6 hours              February 25 2024 - October 26 2024        
22 - Flap                                         80.1 hours              September 18 2023 - October 9 2024
23 - Aileron Actuation                                                           
24 - Wing Tip                                   

OP38 - Aileron Trim                       2.9 hours ðŸ”§                                       
                                                                    
Total                                             418.2 hours

Fuselage

25 - Mid Fuselage Bulkheads                   28.5 hours             December 9 2024 - January 17 2025
26 - Mid Fuse Ribs & Bottom Skins         66.2 hours             January 1 2025 - June 6 2025
27 - Firewall                                                 43.2 hours ðŸ”§.           Started February 27 2025
28 - Fwd Fuse Ribs, Bulkheads &            27.9 hours ðŸ”§.           Started March 5 2025
        Bottom Skin

Mods

Control Approach - Rudder Pedals            3.4 hours ðŸ”§

Total                                                           169.2 hours

Finishing

Total                                                               0.0 hours

Total Build Time          1040.0 hours


Priming

Total                                               133.5 hours (not included in build time totals)