Time Tracker
Build started June 29, 2022
🔧 = in progress
✅ = completed
Empennage and Tail Cone
6 - Vertical Stabilizer 34.3 hours ✅ June 29 - September 5 2022
7 - Rudder 41.7 hours ✅ July 8 - September 4 2022
8 - Horizontal Stabilizer 87.7 hours ✅ July 16 - October 24 2022
9 - Elevators 92.3 hours 🔧 Started September 14 2022
10 - Tail Cone 164.8 hours ✅ January 8 2023 - June 3 2024
11 - Empennage Attach 7.8 hours 🔧 Started August 15 2023
Total 428.6 hours
Wings
13 - Main Spar 39.9 hours ✅ July 6 2023 - January 13 2024
14 - Wing Ribs 48.8 hours ✅ August 27 2023 - March 27 2024
15 - Rear Spar 32.7 hours ✅ August 28 2023 - April 5 2024
16 - Top Wing Skins 60.6 hours ✅ January 19 2024 - June 27 2024
17 - Outboard Leading Edge 56.0 hours ✅ September 18 2023 - June 30 2024
18 - Fuel Tank 38.7 hours 🔧 Started October 1 2023
19 - Stall Warning System SKIPPED
20 - Bottom Wing Skin 8.9 hours 🔧 Started May 25 2024
21 - Aileron 49.6 hours ✅ February 25 2024 - October 26 2024
22 - Flap 80.1 hours ✅ September 18 2023 - October 9 2024
23 - Aileron Actuation
24 - Wing Tip
Total 415.3 hours
Fuselage
Total 0.0 hours
Finishing
Total 0.0 hours
Total Build Time 843.6 hours
Priming
Total 102.2 hours (not included in build time totals)